Docket: 17-042-U

Style: IN THE MATTER OF THE APPLICATION OF C & L ELECTRIC COOPERATIVE CORPORATION FOR A CERTIFICATE OF PUBLIC CONVENIENCE AND NECESSITY (CCN) TO CONSTRUCT, OWN, AND OPERATE A 115 KV TRANSMISSION LINE TO EXTEND APPROXIMATELY 2.O MILES SOUTHEAST FROM THE HERMITAGE SOUTH SWITCHING STATION TO THE EXISTING HERMITAGE METER POINT IN BRADLEY COUNTY, ARKANSAS

Electronic: True

Open: True

Service List: View

Commission Staff: View


Document Numbers omitted from the following list of documents are assigned to Affidavits of Non-disclosure. Click here to view this Docket with Affidavits of Non-disclosure included.

Company Name Docket Role
C & L Electric Cooperative Corporation Initiating Party
APSC General Staff Party
C & L Electric Cooperative Corporation Party
Commission Party
File Date/Time
Description
8:24:00 AM
9/7/2017
1. C & L Electric Cooperative Corporation submits an Application for a Certificate of Public Convenience and Necessity to construct, operate, and maintain a 115 kV transmission line to extend approximately 2.0 miles southeast from the Hermitage South Switching Station, a three-breaker ring bus owned by AECC, and terminating at C&L's new Hermitage Substation which is to be constructed adjacent to the existing Hermitage meter point. Testimony of Adam L. Toth is also included. Establishes Docket. Ks
10:00:00 AM
9/11/2017
2. ORDER NO. 1 (COMMISSION) hereby designates Administrative Law Judge Susan D'Auteuil as Presiding Officer in this Docket. Ks